Chopper to be Used for New Overhead Electrical Cable Installation in Middlebury; Brief I-84 Ramp Closures Required
The Connecticut Department of Transportation is announcing that CL&P will be using a helicopter to install four new overhead electrical cables across the Exit 17 on ramp to I-84 Westbound and across Route 63 (Straits Turnpike) located east of the on ramp in Middlebury on Saturday, March 29, 2014, between the hours of 8 a.m. and 11 a.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542552
Friday, March 28, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Rehabilitation of Bridge No. 02501 and 02502 on Route 82 over Succor Brook in the Town of East Haddam
The Connecticut Department of Transportation is announcing the recommencing of the replacement of Bridge No. 02501 and 02502 on Route 82 over the Succor Brook in East Haddam beginning April 4, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542536
The Connecticut Department of Transportation is announcing the recommencing of the replacement of Bridge No. 02501 and 02502 on Route 82 over the Succor Brook in East Haddam beginning April 4, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542536
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Lane Closures for Bridge Inspections March 30-April 4, 2014
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 30 – April 4, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542530
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 30 – April 4, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542530
Thursday, March 27, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Multiple Nighttime I-84 Ramp Closures in Hartford, April 1 – 4
The Connecticut Department of Transportation is announcing that the I-84 westbound on ramp from Capitol Avenue will be closed each night starting Tuesday, April 1, to Friday, April 4, 2014, between the hours of 10:00 p.m. to 5:00 a.m. The I-84 eastbound off ramp to Asylum Street (Exit 48A) will also be closed each night on April 1 and April 2, 2014, between the hours of 10:00 p.m. to 5:00 a.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542416
The Connecticut Department of Transportation is announcing that the I-84 westbound on ramp from Capitol Avenue will be closed each night starting Tuesday, April 1, to Friday, April 4, 2014, between the hours of 10:00 p.m. to 5:00 a.m. The I-84 eastbound off ramp to Asylum Street (Exit 48A) will also be closed each night on April 1 and April 2, 2014, between the hours of 10:00 p.m. to 5:00 a.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542416
Tuesday, March 25, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Nighttime Lane Closures in Hartford on I-91 Northbound and Southbound, in the vicinity of the Jennings Road Overpass (Exit 33), occurring Sunday, March 30, to Friday, April 4, 2014
The Connecticut Department of Transportation is announcing that there will be various lane closures along the I-91 northbound and southbound routes in the vicinity of the Jennings Road overpass (Exit 33), from Sunday, March 30, to Friday, April 4, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542260
The Connecticut Department of Transportation is announcing that there will be various lane closures along the I-91 northbound and southbound routes in the vicinity of the Jennings Road overpass (Exit 33), from Sunday, March 30, to Friday, April 4, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542260
ConnDOT eAlert: News from the Connecticut Department of Transportation
Ribbon Cut for Westbrook Train Station
Connecticut Department of Transportation Commissioner James P. Redeker joined Westbrook First Selectman Noel Bishop and other regional and local officials today to cut a ribbon and formally open the new Westbrook train station serving Shore Line East customers.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542250
Connecticut Department of Transportation Commissioner James P. Redeker joined Westbrook First Selectman Noel Bishop and other regional and local officials today to cut a ribbon and formally open the new Westbrook train station serving Shore Line East customers.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542250
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Rehabilitation of Culverts on Route 2 in Colchester and Preston to Begin on April 1, 2014
The Connecticut Department of Transportation is announcing that the project for the rehabilitation of culvert numbers 05456 (Route 2 over Crowley Brook), 06675 (Route 2 over Myers Brook) and 06669 (Route 2 over unnamed brook) in Colchester and Preston is beginning on April 1, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542154
The Connecticut Department of Transportation is announcing that the project for the rehabilitation of culvert numbers 05456 (Route 2 over Crowley Brook), 06675 (Route 2 over Myers Brook) and 06669 (Route 2 over unnamed brook) in Colchester and Preston is beginning on April 1, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542154
Monday, March 24, 2014
ConnDOT eAlert: News from the Connecticut Department of Transportation
Train Monitoring Systems Planned for Metro-North Railroad and LIRR
Metro-North Railroad and the Long Island Rail Road plan to install monitoring equipment designed to detect defective or overheated wheels and loads of freight trains that operate on publicly owned tracks and convey that information in real time to the railroads' control centers.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542176
Metro-North Railroad and the Long Island Rail Road plan to install monitoring equipment designed to detect defective or overheated wheels and loads of freight trains that operate on publicly owned tracks and convey that information in real time to the railroads' control centers.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542176
ConnDOT eAlert: News from the Connecticut Department of Transportation
Metro-North Signal Upgrades Complete at Curves and Bridges
MTA Metro-North Railroad has completed permanent changes to its signal system to ensure automatic speed enforcement at five critical curves and five moveable bridges in New York and Connecticut, more than five months ahead of schedule.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542174
MTA Metro-North Railroad has completed permanent changes to its signal system to ensure automatic speed enforcement at five critical curves and five moveable bridges in New York and Connecticut, more than five months ahead of schedule.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542174
ConnDOT eAlert: News from the Connecticut Department of Transportation
Metro-North to Hold Informal Customer Forums at Stations
Making good on a pledge to increase openness and transparency, MTA Metro-North Railroad will hold six informal meeting at Grand Central and outlying stations in an effort to engage customers in a dialogue with senior management of the railroad, including the new president, Joseph Giulietti.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542172
Making good on a pledge to increase openness and transparency, MTA Metro-North Railroad will hold six informal meeting at Grand Central and outlying stations in an effort to engage customers in a dialogue with senior management of the railroad, including the new president, Joseph Giulietti.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=1373&Q=542172
Friday, March 21, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Lane Closures for Bridge Inspections March 24 - 30, 2014
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 24 - 30, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542066
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 24 - 30, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542066
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Nighttime Bridge Maintenance I-91 in New Haven; Lane Closures Required
The Connecticut Department of Transportation is announcing that a nighttime bridge maintenance project will be performed on I-91 Southbound in New Haven between the hours of 9 p.m. and 5 a.m., Tuesday-Thursday, March 25-27, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542064
The Connecticut Department of Transportation is announcing that a nighttime bridge maintenance project will be performed on I-91 Southbound in New Haven between the hours of 9 p.m. and 5 a.m., Tuesday-Thursday, March 25-27, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542064
Thursday, March 20, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Public Information Meeting Concerning Construction of the Waterbury Bus Maintenance Facility in the Town of Watertown
The Connecticut Department of Transportation (Department) will conduct a public information meeting concerning the construction of the Waterbury Bus Maintenance Facility on Wednesday, April 16, 2014, at 7:00 p.m. at the Watertown High School Auditorium, 324 French Street in Watertown. An informal question and answer session will begin at 6:30 p.m. followed by a formal design presentation at 7:00 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542032
The Connecticut Department of Transportation (Department) will conduct a public information meeting concerning the construction of the Waterbury Bus Maintenance Facility on Wednesday, April 16, 2014, at 7:00 p.m. at the Watertown High School Auditorium, 324 French Street in Watertown. An informal question and answer session will begin at 6:30 p.m. followed by a formal design presentation at 7:00 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542032
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
New Overhead Electric Line to be Installed across Route 8 in Watertown; Helicopter to be Used
The Connecticut Department of Transportation is announcing that CL&P will be installing a new overhead electric line across Route 8 between exits 36 and 37 in Watertown on Saturday, March 22, 2014, between the hours of 1 p.m. and 4 p.m. A helicopter will be part of the operation.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542014
The Connecticut Department of Transportation is announcing that CL&P will be installing a new overhead electric line across Route 8 between exits 36 and 37 in Watertown on Saturday, March 22, 2014, between the hours of 1 p.m. and 4 p.m. A helicopter will be part of the operation.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Rehabilitation of Bridge Carrying Interstate 691 over Lewis Avenue in the City of Meriden
The Connecticut Department of Transportation is announcing that work will begin Monday, March 24, 2014, on Bridge No. 02069 that carries Interstate 691 over Lewis Avenue in the town of Meriden.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542000
The Connecticut Department of Transportation is announcing that work will begin Monday, March 24, 2014, on Bridge No. 02069 that carries Interstate 691 over Lewis Avenue in the town of Meriden.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=542000
Tuesday, March 18, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Traffic Shift Scheduled for the Putnam Bridge Carrying Route 3 over the Connecticut River in the Towns of Wethersfield and Glastonbury
The Connecticut Department of Transportation is announcing a traffic shift involving installation of new pavement markings and shifting of temporary concrete barriers on the Putnam Bridge. The shift will begin at 6:00 AM on Saturday, March 22, 2014 and will be completed that day. Motorists may experience lane closures while Route 3 Southbound is being shifted onto a recently reconstructed portion of the north side of the bridge and Route 3 Northbound is shifted to the center of the bridge. The shift will allow construction crews to begin work on the south side of the structure.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541858
The Connecticut Department of Transportation is announcing a traffic shift involving installation of new pavement markings and shifting of temporary concrete barriers on the Putnam Bridge. The shift will begin at 6:00 AM on Saturday, March 22, 2014 and will be completed that day. Motorists may experience lane closures while Route 3 Southbound is being shifted onto a recently reconstructed portion of the north side of the bridge and Route 3 Northbound is shifted to the center of the bridge. The shift will allow construction crews to begin work on the south side of the structure.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541858
Monday, March 17, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Rehabilitation of Salt Sheds in the Towns of Darien, Trumbull, Westport and Wilton
The Connecticut Department of Transportation's Office of Engineering is developing plans for the rehabilitation of existing salt sheds at 65 Brookside Drive in Darien, Route 111 Monroe Turnpike in Trumbull, 900 Post Road East in Westport and on Route 7 at Route 33 in Wilton. The main purpose of this project is to perform maintenance repairs to aging salt sheds.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541750
The Connecticut Department of Transportation's Office of Engineering is developing plans for the rehabilitation of existing salt sheds at 65 Brookside Drive in Darien, Route 111 Monroe Turnpike in Trumbull, 900 Post Road East in Westport and on Route 7 at Route 33 in Wilton. The main purpose of this project is to perform maintenance repairs to aging salt sheds.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541750
Friday, March 14, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Rehabilitation of Bridge #3290 and #3291 (Rte. 9 NB & SB over Nedobity Road), Haddam
The Connecticut Department of Transportation is announcing the start of work to rehabilitate two bridges on Route 9 over Nedobity Road in the Town of Haddam, beginning March 12, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541714
The Connecticut Department of Transportation is announcing the start of work to rehabilitate two bridges on Route 9 over Nedobity Road in the Town of Haddam, beginning March 12, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541714
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Lane Closures for Bridge Inspections March 17-21, 2014
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 17 - 21, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541704
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 17 - 21, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541704
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Installation of Pedestrian Bridge over Washington Boulevard in the City of Stamford
The Connecticut Department of Transportation is announcing that installation of the pedestrian bridge superstructure is expected to occur the weekends of March 28, April 4, and April 11, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541696
The Connecticut Department of Transportation is announcing that installation of the pedestrian bridge superstructure is expected to occur the weekends of March 28, April 4, and April 11, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541696
Tuesday, March 11, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Nighttime Bridge Maintenance on I-95 in New Haven; Lane Closure Required
The Connecticut Department of Transportation is announcing that a nighttime maintenance project will be performed on the I-95 bridge over the West River in New Haven, from 9 p.m. Tuesday to 5 a.m. Thursday, March 11-13, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541466
The Connecticut Department of Transportation is announcing that a nighttime maintenance project will be performed on the I-95 bridge over the West River in New Haven, from 9 p.m. Tuesday to 5 a.m. Thursday, March 11-13, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541466
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Tree Removal along Route 72 in Plainville
The Connecticut Department of Transportation is announcing that tree removal work will be performed in the center median on Route 72 in Plainville on Tuesday, March 18, 2014, from 9 a.m. to 3 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541434
The Connecticut Department of Transportation is announcing that tree removal work will be performed in the center median on Route 72 in Plainville on Tuesday, March 18, 2014, from 9 a.m. to 3 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541434
Friday, March 7, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Lane Closures for Bridge Inspections March 9 - 14, 2014
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 9 - 14, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541184
Lane closures for bridge safety inspections and evaluations will be required around Connecticut, March 9 - 14, 2014. View the complete list and plan ahead.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541184
Thursday, March 6, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Rehabilitation of Culverts 06667, 06679, and 06701 on Routes 69, 219, and 254 in the towns of Burlington, Granby, and Thomaston
The Connecticut Department of Transportation is announcing that work to rehabilitate culverts located in the towns of Burlington, Granby, and Thomaston will begin April 1, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541120
The Connecticut Department of Transportation is announcing that work to rehabilitate culverts located in the towns of Burlington, Granby, and Thomaston will begin April 1, 2014.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541120
Wednesday, March 5, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Public Information Meeting Concerning Improvements to Hartford Union Station
The Connecticut Department of Transportation (Department) will conduct a Public Information Meeting concerning Hartford Union Station. The meeting will be on Thursday, March 27, 2014 at 4:00 p.m. in the Great Hall of Hartford Union Station, One Union Place in Hartford.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541106
The Connecticut Department of Transportation (Department) will conduct a Public Information Meeting concerning Hartford Union Station. The meeting will be on Thursday, March 27, 2014 at 4:00 p.m. in the Great Hall of Hartford Union Station, One Union Place in Hartford.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541106
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
I-84 Westbound On-Ramp from Capitol Avenue in Hartford to be Closed for Overnight Work March 10-11, 2014; Detour Required
The Connecticut Department of Transportation is announcing that I-84 westbound on ramp from Capitol Avenue will be closed overnight on Monday, March 10, and Tuesday, March 11, 2014, from 10:00 p.m. to 5:00 a.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541002
The Connecticut Department of Transportation is announcing that I-84 westbound on ramp from Capitol Avenue will be closed overnight on Monday, March 10, and Tuesday, March 11, 2014, from 10:00 p.m. to 5:00 a.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=541002
Tuesday, March 4, 2014
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
CL&P To Remove Old Electric Lines near Exit 17 on I-84 and Route 63 in Middlebury; Lane Closure Required
The Connecticut Department of Transportation is announcing that Connecticut Light & Power will be removing old overhead electric lines across the Exit 17 on ramp on I-84 and across Route 63 in Middlebury on Wednesday, March 5, 2014, between the hours of 9 a.m. and 3 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=540978
The Connecticut Department of Transportation is announcing that Connecticut Light & Power will be removing old overhead electric lines across the Exit 17 on ramp on I-84 and across Route 63 in Middlebury on Wednesday, March 5, 2014, between the hours of 9 a.m. and 3 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=540978
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Tree Removal along Route 5/15 Northbound in Hartford; Lane Closure Required
The Connecticut Department of Transportation is announcing that tree removal work will be performed on Route 5/15 Northbound in Hartford on Wednesday, March 5, 2014, from 9 a.m. to 3 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=540968
The Connecticut Department of Transportation is announcing that tree removal work will be performed on Route 5/15 Northbound in Hartford on Wednesday, March 5, 2014, from 9 a.m. to 3 p.m.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=540968
ConnDOT eAlert: Construction News from the Connecticut Department of Transportation
Reconstruction of Christian Street from Towner Lane to Robinson Lane in Oxford; Lane Closures Required
The Connecticut Department of Transportation is announcing that work will begin March 11, 2014, on the reconstruction of Christian Street from Towner Lane to Robinson Lane in the town of Oxford.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=540966
The Connecticut Department of Transportation is announcing that work will begin March 11, 2014, on the reconstruction of Christian Street from Towner Lane to Robinson Lane in the town of Oxford.
For more information, please visit the ConnDOT website: http://www.ct.gov/dot/cwp/view.asp?a=2135&Q=540966